# How did a 2025 UNOPS Laos tender set the oxygen plant room and backup?

**What did UNOPS's clarifications to its 2025 Laos medical gas tender say about the plant room, oxygen redundancy, cylinder backup and power?**

According to the clarifications on UNOPS invitation to bid ITB/2025/55458 (January to February 2025), the Laos plant room was set at 72 sqm with one 2 m wide door, the oxygen supply needed a main line and a back-up line, and the UPS needed at least 30 minutes of autonomy.

This answer reads the clarifications and amendments on one public UNGM notice. The answers quoted are UNOPS's replies to questions from prospective bidders, not general design rules. The tender is closed, and the values below are those of this one hospital project.

## What UNOPS answered

| Topic | UNOPS answer or amendment |
|---|---|
| Plant room floor area | Revised to 45 sqm on 20 January 2025 (amendment 3), then to 72 sqm in answers of 29 January 2025, which said two walls would be demolished; UNOPS said the space could not be increased to 170 sqm |
| Plant room door | One door, 2 m wide and 2.6 m high |
| Oxygen redundancy | Two independent lines able to guarantee continuous supply, one main line and one back-up line; the second generator was for back-up and filling |
| Compressor type | Asked to offer standard oiled compressors instead of oil-free ones, UNOPS replied: "Please adhere to the requirement." |
| Cylinder back-up | A 2x10 automatic change over was accepted as sufficient |
| Medical air | The requirement was for 3 compressors |
| Vacuum | At least two pumps |
| Single failure | The design had to keep supplying oxygen and medical air under a single failure of any component |
| UPS | UPS devices protecting the controllers of the oxygen and medical air generation systems against micro power outages had to provide at least 30 minutes of autonomy (amendment 8, 3 February 2025) |
| Oxygen booster output | Lowered from at least 80 m³/hr to at least 30 m³/hr (amendment 7, 3 February 2025) |

## What the design memory had to cover

UNOPS told bidders to explain their design criteria in a document called the design memory, including the equipment, capacity, technology, number of compression units and type of monitoring, and a review of the design according to HTM 02-01:2006, with schematic diagrams. The tender cites that 2006 edition; HTM 02-01 is NHS England guidance, and for its current edition see [what changed in the 2026 edition of HTM 02-01](https://library.ultracontrolo.com/answers/what-changed-in-htm-02-01/).

## What it means for a supplier

The clarifications show how much of a plant's design was settled by questions during the bidding period: room size changed twice, and the booster output and the UPS were amended after bidders asked. Anyone reading a similar tender should check the amendments and clarifications as well as the main documents. For backup power in general, see [whether a PSA plant needs a backup generator or UPS](https://library.ultracontrolo.com/answers/does-a-psa-plant-need-a-generator-or-ups/).

### Was the plant room finished when the tender ran?

No. UNOPS said the space was not ready and that works were to be completed within the next two months.

### Does this set a rule for other countries?

No. These are answers to bidders on one UNOPS tender for Laos.

## Sources

- [UNOPS, ITB/2025/55458 Procurement of Medical Gas and Patient Support Systems for Laos, UNGM notice published 8 January 2025 with its clarifications and amendments, read 20 November 2026](https://www.ungm.org/Public/Notice/256719)

Reviewed: 2026-11-20. Ultra Controlo engineering. https://library.ultracontrolo.com/answers/how-did-unops-set-the-plant-room-and-backup-in-its-2025-laos-tender/