# How reliable is grid electricity in Zambia?

**How reliable is the national grid in Zambia according to the 2024 Afrobarometer survey published in May 2026?**

According to Afrobarometer Dispatch No. 1178 of 7 May 2026, based on a July 2024 survey of 1,200 adults, 55% of Zambians live in zones served by the ZESCO grid, 28% say their household is connected and only 4% have a connection that they say works most or all of the time.

This answer reads Afrobarometer Dispatch No. 1178, a 15-page PDF published on 7 May 2026. It reports a household survey, not a measurement of the grid and not a study of hospitals. The fieldwork was done in July 2024, during the electricity crisis the dispatch describes.

## What the survey found

- Afrobarometer interviewed a nationally representative sample of 1,200 adult citizens between 8 and 28 July 2024, with a margin of error of plus or minus 3 percentage points.
- 55% live in zones served by the ZESCO grid, but only 28% say their households are connected to it.
- Among those who are connected, 15% say their electricity works most or all of the time.
- Combining the two rates, the dispatch says 4% of all Zambians enjoy a reliable supply from the national grid.
- 47% say their households use power from a source other than the ZESCO grid, mostly solar panels (83% of that group).

## The background the dispatch gives

The dispatch says hydropower accounts for 84% of electricity supply, that the shortfall between generation and demand reached 1,600 megawatts in February 2024, and that ZESCO has implemented load shedding for up to 21 hours per day, citing a 2024 source. It says the crisis has been attributed to low reservoir levels and the worst drought in the past five decades.

## What the dispatch does not say

The survey asks households about their own supply, so its percentages cannot be read as the supply to a hospital. The text read does not discuss health facilities or oxygen. Conditions may also have changed since July 2024. For what to plan around when a hospital's mains supply is poor, see [whether a PSA plant needs a generator or UPS](https://library.ultracontrolo.com/answers/does-a-psa-plant-need-a-generator-or-ups/) and [whether a PSA plant can run on solar power](https://library.ultracontrolo.com/answers/can-a-psa-oxygen-plant-run-on-solar-power/). For health facilities across the region, see [how reliable electricity is in sub-Saharan African health facilities](https://library.ultracontrolo.com/answers/how-reliable-is-electricity-in-sub-saharan-african-health-facilities/).

### Is this the grid reliability of Zambian hospitals?

No. It is a household survey from July 2024; it does not give a figure for hospitals.

## Sources

- [Afrobarometer, Dispatch No. 1178, 'Amid electricity crisis, Zambians favour ending state monopoly, investing in solar and wind power', 7 May 2026, read 19 November 2026](https://www.afrobarometer.org/wp-content/uploads/2026/05/AD1178-Zambians-favour-ending-ZESCO-monopoly-investing-in-solar-and-wind-power-Afrobarometer-6may26.pdf)

Reviewed: 2026-11-19. Ultra Controlo engineering. https://library.ultracontrolo.com/answers/how-reliable-is-grid-electricity-in-zambia/