# What did UNOPS ask of bidders in its 2025 Laos medical gas tender?

**What did UNOPS ask of bidders in its January 2025 invitation to bid for medical gas and patient support systems for Laos?**

According to the UNGM notice for UNOPS invitation to bid ITB/2025/55458, published on 8 January 2025, UNOPS sought medical gas and patient support systems for Lao PDR; after extensions the deadline was 13 February 2025, so the tender has closed.

This answer reads the public UNGM notice for one UNOPS tender, including the amendments and clarifications UNOPS added to it. It is a closed tender, so it is a record of what was asked, not an open opportunity. The notice does not name a funder or the hospital. It says that the full tender details need a UNOPS vendor login on UNGM, so this answer uses only the notice text, its amendments and its clarifications.

## The tender

| Item | What the notice says |
|---|---|
| Reference | ITB/2025/55458, invitation to bid |
| Title | Procurement of Medical Gas and Patient Support Systems for Laos |
| Beneficiary | Lao People's Democratic Republic |
| Published | 8 January 2025 |
| Deadline | 13 February 2025 at 05:00 GMT, extended to 6 February by amendment 4 and to 13 February by amendment 6; the notice is marked expired |
| How to respond | Through the UNOPS eSourcing system via the UNGM portal, as a registered UNOPS vendor |

## What the clarifications set for the scope and terms

- Piping from the main plant to the beds was outside the tender and was to be provided by a separate contractor. The supplier was to connect the medical gas plants to a manifold in the plant room, and the bed head units to the piping available at wall level.
- In answers on the bed head units, UNOPS said civil works were not in the selected supplier's scope and would be provided by a separate contractor, and that pre-installation requirements were to be submitted after the award and at least one month before the planned installation.
- In the same answers, UNOPS said the availability of spares and consumables requested in the tender documents was mandatory and could not be met by a one-time upfront purchase. The bidder question it was answering, on the bed head units, refers to 8 years of availability.
- Payment was 100% of the price of the goods, including related services, within 30 calendar days of UNOPS receiving the payment documentation to its satisfaction.

## What it means for a supplier

The notice shows a UNOPS plant tender for Laos that separated the supplier's equipment from the building works and from the piping to the beds, and that attached a mandatory spares and consumables availability requirement. These terms belong to this one tender and are not a general rule for Laos or for UNOPS. For the portal where UNOPS published the notice, see [UNGM (United Nations Global Marketplace)](https://library.ultracontrolo.com/glossary/ungm/); for the technical side of the same tender, see [the plant room and backup clarifications](https://library.ultracontrolo.com/answers/how-did-unops-set-the-plant-room-and-backup-in-its-2025-laos-tender/).

### Is this tender still open?

No. After the extensions in amendments 4 and 6, the deadline was 13 February 2025, and the notice is marked expired.

### Does the notice say who paid for the equipment?

No. The notice does not state a funding source.

## Sources

- [UNOPS, ITB/2025/55458 Procurement of Medical Gas and Patient Support Systems for Laos, UNGM notice published 8 January 2025 with its clarifications and amendments, read 20 November 2026](https://www.ungm.org/Public/Notice/256719)

Reviewed: 2026-11-20. Ultra Controlo engineering. https://library.ultracontrolo.com/answers/what-did-unops-ask-of-bidders-in-its-2025-laos-medical-gas-tender/