# What does a Cameroon tender ask of an oxygen plant contractor?

**What did the Douala General Hospital tender dossier for maintenance and operation of its oxygen production unit require of bidders and of the contractor?**

According to Douala General Hospital's tender dossier of November 2024, its 12-month maintenance and operation contract for the oxygen production unit (2025 budget year) was open to Cameroonian-law companies specialised in medical device maintenance, with an eliminatory technical score of 85 out of 100.

## Who could bid

- A national open tender under the urgency procedure, with a single lot and offline submission.
- Participation was open to companies under Cameroonian law specialised in medical device maintenance with the necessary financial capacity.
- Eliminatory criteria included a missing bid security, a missing site-visit declaration, a missing representation contract with the manufacturer of the oxygen unit, and a technical score below 85 out of 100.

## What the contractor had to do

- Check daily that the unit works and produces medical oxygen without interruption.
- Carry out preventive maintenance and repair, and produce intervention sheets for every fault.
- Submit a maintenance calendar within 3 weeks of the start order, and produce monthly reports and an annual failure report covering cause, solution, time and cost.
- Supply the parts needed for scheduled maintenance or repair; parts for interventions the hospital requested outside preventive maintenance were at the hospital's expense, and replaced parts became the hospital's property.

## Key staff and unit

Three key staff were required: a technician with at least two years of practical experience, a supervising engineer with at least two years, and a mission head with at least three years including specific medical device maintenance missions. The terms describe the hospital's unit as a screw-compressor plant with a 150 bar filling ramp for cylinders from 5 to 50 litres and a stated capacity of 20 cylinders in 16 hours.

This is one hospital's tender, not a national rule. For related guidance, see [what manufacturer authorisation means in an oxygen tender](https://library.ultracontrolo.com/answers/what-is-a-manufacturer-authorisation-in-an-oxygen-tender/), [whether a tender should require local after-sales service](https://library.ultracontrolo.com/answers/should-an-oxygen-tender-require-local-after-sales-service/) and [how Cameroon hospital tenders are published](https://library.ultracontrolo.com/answers/how-are-hospital-tenders-published-in-cameroon/).

### Is this a national requirement for oxygen plant maintenance in Cameroon?

No. It is the content of one hospital's tender dossier and says nothing about national rules.

## Sources

- [Douala General Hospital, tender dossier for maintenance and operation of the oxygen production unit (November 2024, budget year 2025)](https://pridesoft.armp.cm/_lib/file/doc/0903/2024/11/27/HGD/DAO%20maintenance%20et%20exploitation%20de%20la%20centrale%20%C3%A0%20oxyg%C3%A8ne%202025%202%20TEMPS.docx)

Reviewed: 2026-11-19. Ultra Controlo engineering. https://library.ultracontrolo.com/answers/what-does-a-cameroon-hospital-ask-of-an-oxygen-plant-maintenance-contractor/