How can a ministry train enough technicians for its oxygen plants?
How can a ministry of health build national biomedical technician capacity to operate and repair its oxygen plants?
Short answer
World Health Assembly resolution WHA76.3 (2023) urges Member States to provide adequate numbers of qualified staff, including engineers, to select, set up, operate and maintain oxygen equipment; PATH (2023) recommends that ministries of health assess workforce capacity, develop biomedical engineering and technician training programmes and deploy retention schemes.
What governments have been asked to do
WHA76.3 (30 May 2023) urges Member States to provide for adequate numbers of qualified staff, including engineers, to establish demand for, select, set up, operate and maintain oxygen production, storage and distribution equipment and infrastructure, and asks WHO to support them with guidelines, technical specifications, forecasting tools and training materials, and to support their efforts to provide adequate, predictable and sustainable financing for the trained workforce needed to install, operate and maintain oxygen systems safely. WHO's Foundations of medical oxygen systems (2023) lists a trained clinical and technical workforce among the requirements for access to oxygen, and says training on oxygen generation systems should be generic, so that the workforce can operate and maintain any of the systems.
Where the gap is
PATH's analysis of PSA plant failures (November 2023) found that few of the assessed facilities had on-site staff with technical training in plant maintenance and repair, that many countries have low numbers of trained biomedical engineers and technicians because of insufficient local training capacity and difficulty retaining skilled workers, and that technicians have at times taught themselves the basic skills to run a plant. It also reports that some suppliers restrict training and documentation such as service manuals and spare part lists in local languages.
What PATH recommends (November 2023)
- Ministries of health: assess workforce capacity and allocate biomedical engineers and technicians according to each facility's needs.
- Ministries of health: develop biomedical engineering and technician training programmes; more broadly, PATH also recommends improving countries' biomedical engineering capacity through educational, training and retention programmes.
- Ministries of health: deploy retention schemes with fair compensation, work-life balance and clear growth and development paths.
- Across the plant life cycle: upskill on-site technicians on how to assess plants and obtain support, and conduct regular training on plant operation and maintenance, especially when there is staff turnover.
- Public procurement entities: stipulate in tenders independent quality checks, training, operating and maintenance manuals and spare part lists in the applicable local languages.
Training at each level
| Course or document | For whom | When or how |
|---|---|---|
| Global Fund management training (25 April 2025), two days | Ministry of health senior leaders, hospital directors and those supervising PSA maintenance teams | Early in the PSA plant procurement process |
| Global Fund maintenance training (24 April 2025), five days on site | Biomedical engineers and technicians, facilities managers, hospital operations staff | Immediately after installation and commissioning, with ongoing training and virtual support; in English and French |
| Global Fund repair and electrical assessment training (25 April 2025) | A small team that travels to assess different PSA plants | So that local staff can carry out repair assessments independently |
| Training of trainers, in the Global Fund staffing note (11 April 2025) | Engineers | Hybrid classroom and practical training on how to train plant operators in daily maintenance and troubleshooting |
Global Fund sustainability guidance (22 August 2024) asks for a national strategy for oxygen investment and capacity building, for the competencies needed to be defined before the manufacturer's training, and for capacity-building programmes to supplement supplier training. In UNDP procurement, REQ-OXY-001 (effective 1 January 2025) asks country offices to facilitate ongoing training for end users on preventive maintenance, troubleshooting, energy optimisation and resource efficiency, and WHO's 2024 technical specifications suggest a continuous development training programme paired with the service level agreement. What the supplier itself should teach at handover is on what training a PSA supplier should provide, and staffing levels on what staff are needed to run a PSA plant.
Ultra Controlo
On large ULTRAOX plants, installation, initial start-up and staff training are supervised by Ultra Controlo factory technicians (ULTRAOX SC datasheet, p. 3), and through UltraCare the company selects people in each country and trains technicians to look after its equipment (ULTRAOX datasheet 2022, p. 6).
More questions
Should technicians be trained on one brand of PSA plant?
WHO's Foundations of medical oxygen systems (2023) says training on oxygen generation systems should be generic in nature, so that the workforce is skilled to operate and maintain any of the systems.
When should ministry managers be trained?
The Global Fund recommends its two-day management course early in the PSA plant procurement process, to support procurement decisions and service contract negotiations.
Sources
- World Health Assembly resolution WHA76.3, Increasing access to medical oxygen (30 May 2023)
- WHO, Foundations of medical oxygen systems (17 February 2023)
- PATH, Pressure swing adsorption plants: Common issues and solutions to prevent future disrepair (November 2023)
- Global Fund / Build Health International, Management Training for PSA Medical Oxygen Plants (25 April 2025)
- Global Fund / Build Health International, Maintenance Training for PSA Medical Oxygen Plants (24 April 2025)
- Global Fund / Build Health International, Repair and Electrical Assessment Training for PSA Medical Oxygen Plants (25 April 2025)
- Global Fund / Build Health International, Briefing Note: Oxygen Plant Staffing (11 April 2025)
- Global Fund / Build Health International, Overview: Sustainability Guidance for PSA Oxygen Plants (22 August 2024)
- UNDP, REQ-OXY-001 v01, Technical and regulatory requirements for oxygen plants (effective 1 January 2025), section 7.6
- WHO, Technical specifications for health facility based medical oxygen systems (31 December 2024), oxygen generator plant table, line 38
- ULTRAOX SC datasheet, p. 3
- ULTRAOX datasheet 2022, p. 6
Ultra Controlo figures come from its technical datasheets. Third-party facts were read at the source on the date shown.
Related
- AnswersWhat training should a PSA plant supplier provide?
- AnswersWhat staff are needed to run a PSA oxygen plant?
- AnswersWhat does resolution WHA76.3 on medical oxygen ask?
- AnswersWhat is a national medical oxygen plan?
- AnswersHow can a ministry audit the status of all its oxygen plants?
- AnswersWhy do PSA oxygen plants stop working?