How does the World Bank's Morocco Health Reform Program handle procurement according to its June 2025 status report?
Short answer
The World Bank's implementation status report of 20 June 2025 on the Morocco Health Reform Program (P179014), a Program-for-Results financing approved on 15 June 2023, lists procurement actions that include publishing annual procurement plans by the end of the first quarter and implementing them under existing Moroccan regulations.
The report describes IBRD loan 95540, approved on 15 June 2023, signed on 30 October 2023, effective on 8 January 2024 and closing on 30 September 2028. It rates progress towards the objective, which is to strengthen institutional capacity and governance for quality public health services in the program area, as moderately satisfactory.
Procurement actions in the program action plan
- Procurement plans are to be prepared and implemented under existing regulations, with annual plans published no later than the end of the first quarter of the fiscal year. The report marks this in progress and says the progress report confirms adherence.
- A capacity-strengthening program on the new procurement decree, run by the Trésorerie Générale du Royaume (TGR), is marked completed, with all staff in the relevant department trained.
- An eligibility check clause is to be included in bidding documents so that no person or entity debarred or suspended by the Bank is awarded a contract under the program. The report marks it delayed, saying no progress report with evidence had been submitted.
- A semi-annual reporting mechanism on tenders and procurement-related complaints is also marked delayed for the same reason.
What the report does not say
The report is about governance and primary care reform. It does not mention oxygen plants or medical gases and does not list equipment contracts, so it does not show which hospital tenders will be issued. A supplier looking for Moroccan health tenders should follow the buyers' own notices. For the national portal, see Where are Moroccan public tenders published?
More questions
Does the report list equipment purchases?
No. It lists procurement actions in the program action plan and does not name medical equipment, oxygen plants or contracts.
Sources
Ultra Controlo figures come from its technical datasheets. Third-party facts were read at the source on the date shown.
Related
- AnswersWhere are Moroccan hospital tenders published?
- AnswersHow did UNICEF Morocco run a 2026 equipment quotation request?
- AnswersHow were World Bank-funded purchases for Lebanon's hospitals run?
- AnswersCan a PSA tender set a maximum kWh per cubic metre?
- AnswersDid a Paraguayan maintenance tender keep manufacturer authorisation?
- AnswersWho services Gardner Denver, Elmo Rietschle and Speck in Portugal?