How is a donor-funded oxygen plant handed over to the ministry?
How is ownership and responsibility for a donor-funded oxygen plant handed over to the ministry or hospital at the end of the project?
Short answer
The Global Fund's asset handover checklist (28 May 2025) guides the ministry, facility directors and plant staff through checks of warranty terms, supplier maintenance, budgets, documents, spare parts and tools before an oxygen plant passes to the responsible party; PATH (2023) recommends ownership transition plans for donated plants beyond the initial warranty or coverage period.
The checklist, written by Build Health International for the Global Fund's Project BOXER, is meant to guide the Country Team, Principal Recipient, Sub-Recipient, Ministry of Health, facility directors and plant staff through the handover of an oxygen plant to the responsible party, and to support a clear, orderly transition of equipment and responsibilities. It says it is not exhaustive and can be adapted to different implementation arrangements and country contexts.
Before commissioning
- Key documents received in the agreed language: warranty terms, information on the supplier's maintenance (a contract, service level agreement or questionnaire), the maintenance schedule, and manuals and training materials in the language the operators understand best.
- Warranty terms received, reviewed and understood by the Principal Recipient and the facility, including its administration and plant operators; commissioning should not start until then.
- A preventive maintenance budget planned across the relevant grant cycles, with the host facility confirming that costs the warranty does not cover are in its maintenance budget.
- Spare parts and consumables organised and inventoried, and tools for the operators' exclusive use on the oxygen system.
The checklist adds that active supplier preventive maintenance must be in place, without gaps in service, to keep the warranty valid.
At commissioning
Global Fund commissioning guidance (28 August 2024) says commissioning should conclude with a formal handover meeting between the supplier or its representative and the hospital, allowing both to sign off the completeness of the supplier's work, and that the documents should be handed over in the country's lingua franca. The checklist asks for a signed copy of the commissioning documents to be shared with the facility and the Principal Recipient, and for maintenance logbooks to track maintenance, service and repairs. UNDP (REQ-OXY-001, effective 1 January 2025) asks for the final handover to include end-user acceptance reports, training reports, drawings, test and calibration reports, warranties and manuals, and in its process flow the installation and commissioning stage ends with registering the equipment and officially commissioning the plant. The full list is on what documents come with an oxygen plant handover.
Planning for the years after the project
PATH's report on PSA plant disrepair (November 2023) found that facility managers and plant operators are often not involved in purchasing decisions yet are expected to allocate limited resources to sustain the plants, and that donations can create a dependency on external support to restore or replace them. It recommends ownership transition plans for donated plants beyond the initial warranty or coverage period, more involvement of biomedical engineers and facility managers in purchasing, and, for donors, a robust ownership transition plan built with the recipients and a quantified total cost of ownership.
Global Fund sustainability guidance (22 August 2024) says operational costs such as spare parts, scheduled maintenance, repairs, electricity, diesel, distribution and staff salaries can be integrated into the hospital's annual budget, asks for financial planning over a life cycle it puts at 10 years on average, and says the terms of any maintenance agreement should be fully understood by the service provider, the operators, hospital management and the central governance level; staffing should be planned before installation. UNDP asks its Country Offices to develop a sustainability roadmap with the end users, and the end users to plan and allocate a budget for operation, maintenance and repair.
Two published examples
UNICEF Burundi reported on 17 June 2024 that, besides oxygen plants for four hospitals funded by Canada in partnership with UNICEF, UNICEF had committed to support their maintenance and train the staff in charge of it for one year; the Bururi hospital can sell its surplus to nearby health facilities, and UNICEF writes that the revenue will contribute to running the plant over time. A UNOPS press release of 28 April 2026 reported that Zambia's Minister of Health commissioned the sixth and final plant of a programme implemented by UNOPS with Global Fund funding, where a Global Fund representative said that responsibility now shifts from infrastructure delivery to performance, reporting and sustainability.
Ultra Controlo
For ULTRAOX plants, the ULTRAOX datasheet (2022, p. 6) describes UltraCare: Ultra Controlo selects people in each country, trains technicians to care for its products, and runs an installation post-monitoring system under ISO 13485 with a preventive maintenance and monitoring programme. See what UltraCare is.
More questions
Does the warranty survive the handover of a donor-funded plant?
The Global Fund checklist (2025) says active supplier preventive maintenance must be in place, without gaps in service, to keep the warranty valid, and that the host facility should budget for the costs the warranty does not cover.
Who signs off the handover of an oxygen plant?
Global Fund commissioning guidance (2024) says there should be a formal handover meeting between the supplier and the hospital, allowing both to sign off the completeness of the supplier's work.
Sources
- Global Fund / Build Health International, Checklist for Oxygen Plant Asset Handover (28 May 2025)
- Global Fund / Build Health International, Overview: PSA Oxygen Plant Commissioning Guidelines (28 August 2024)
- UNDP, REQ-OXY-001 V01, Technical & Regulatory Requirements for Oxygen Plants (effective 1 January 2025), sections 6.6 and 7.6, Figure 2
- PATH, Pressure swing adsorption plants: Common issues and solutions to prevent future disrepair (November 2023)
- Global Fund / Build Health International, Overview: Sustainability Guidance for PSA Oxygen Plants (22 August 2024)
- UNICEF Burundi, A l'Hôpital Régional de Bururi, l'usine de production d'oxygène sauve déjà des vies (17 June 2024)
- UNOPS press release, Commissioning of the St Paul's Mission Hospital oxygen production plant (28 April 2026)
- ULTRAOX datasheet 2022, p. 6
Ultra Controlo figures come from its technical datasheets. Third-party facts were read at the source on the date shown.