Oxygen and PSA
How was Mozambique's Monapo hospital PSA oxygen plant procured?
How did a USAID-supported project procure and hand over the PSA oxygen plant at Monapo District Hospital in Mozambique?
Short answer
A December 2022 technical brief from the USAID-supported GHSC-PSM project says it and its partners procured a PSA oxygen plant for Monapo District Hospital in Nampula province over nine months, for delivery to the Ministry of Health in December 2021, and that USAID handed it over in April 2022.
This page describes one donor-supported procurement, not a public tender notice. No Mozambican tender notice for an oxygen plant was found open on the day this page was written. The source is a technical brief by the USAID Global Health Supply Chain Program-Procurement and Supply Management (GHSC-PSM) project, dated December 2022, which describes its COVID-19 support to Mozambique's Ministry of Health.
Why Monapo, and what the plant was expected to do
The brief says Monapo Hospital is 130 km from the provincial capital Nampula and 2,000 km from Maputo, and that its oxygen equipment was in poor condition and unmaintained. A new PSA plant could produce 30 cylinders of oxygen a week for the hospital and for surrounding health facilities. The brief adds that the plant has the capacity to treat 25 severe COVID-19 patients at the same time and to meet the needs of up to 150 patients, for example childhood pneumonia, safe births and basic surgeries.
How the procurement ran
- The project and its partners procured the PSA equipment over nine months, for delivery to the Ministry of Health in December 2021.
- By March 2022 site preparation was almost complete, and non-clinical maintenance staff were trained to operate and sustain the plant.
- In April 2022 USAID officially handed the plant over to the Ministry of Health's Permanent Secretary, in a public ceremony.
What the brief says about keeping it running
The sustainability plan lists a two-year outsourced maintenance contract, a plan to use the plant's over-capacity to supply neighbouring health facilities, continued advocacy to put operating costs in government budgets, refresher training after 6 to 12 months, and a Ministry of Health maintenance programme with a dashboard. A project official quoted in the brief said such a plant is viable compared with other technologies only if it is used and maintained over its 20-year expected lifespan and runs at sufficient capacity, with maintenance funding from year three.
The lesson the project drew
The brief says a feasibility study should come before choosing the location and the technology, and that it should consider other oxygen sources, such as local suppliers and liquid oxygen instead of gas. For the follow-up on training and maintenance in Mozambique, see How is donated oxygen equipment kept running in Mozambique?. This page does not give the plant's make, cost or tender documents, because the brief does not.
More questions
Who handed over the Monapo oxygen plant?
The brief says USAID officially handed the plant over to the Ministry of Health in April 2022, after the GHSC-PSM project and its partners had procured it.
Did the brief say the plant was bought through a public tender?
No. It says the project and its partners procured the equipment over nine months and does not describe a tender notice.
Sources
Ultra Controlo figures come from its technical datasheets. Third-party facts were read at the source on the date shown.
Related
- AnswersHow is donated oxygen equipment kept running in Mozambique?
- AnswersHow much electricity does a PSA oxygen plant use?
- AnswersWhat should a PSA oxygen plant tender specify?
- AnswersCan a containerised oxygen plant be moved?
- AnswersCan a hospital sell surplus oxygen to nearby facilities?
- AnswersCan a hospital with broken gas pipelines use a PSA plant?