What delivery time, warranty, maintenance period and training did Paraguay's Ministry of Health ask bidders to commit to in its World Bank financed 2023 tender for hospital PSA oxygen plants?

Short answer

In the related services list of Addendum 11 of 15 June 2023 to tender 402407, Paraguay's Ministry of Health asked for installation within 160 days of contract signature, a 24 month warranty from commissioning, 48 months of maintenance and 36 hours of maintenance training.

Per lot

Tender 402407 asked for five PSA oxygen plants, one per hospital lot. The DNCP portal shows the tender published on 1 November 2022, with a final bid date of 4 July 2023, which has passed, and the state "Adjudicada" (awarded) when read on 19 November 2026. For each lot the list of related services in Addendum No. 11 sets out four commitments.

  • Assembly, installation and commissioning, including connection to the hospital's installations: 160 days from signing the contract.
  • Warranty: a written warranty from commissioning for 24 months, for technical failures of the plant's components.
  • Maintenance: a preventive and/or corrective maintenance service from commissioning for 48 months.
  • Training: 36 hours for the people responsible for maintenance, given during installation and commissioning.

What the maintenance clause says

The addendum changed the maintenance clause. The earlier text asked for preventive maintenance for 24 months; Addendum No. 11 replaced it with preventive and/or corrective maintenance for 48 months. The clause says all maintenance is done with certified specialised technical assistance, that the operation and maintenance manuals are delivered in Spanish, and that training is given to the health centre's operating staff if a preventive visit changes the operation or the safety system. It also says the maintenance includes the supplies and the damaged spare parts needed to keep the plant working during the period, regardless of the cause of the failure.

The foreign awardee and the delivery time

Addendum No. 11 added that an international company that won the contract needed a technical and legal representative based in Paraguay, to act as the link between the parties. Several bidders asked for a longer delivery time, one proposing 200 days and another at least 300 days, arguing that manufacturing and shipping already took much of the period. The project unit's replies were to follow the tender document. In one reply it explained that the 160 days cover assembly, installation and commissioning, and that the related services come after commissioning.

These are one buyer's terms for one set of plants. The tender pages read for this answer do not say who pays for spare parts after the 48 months. For the general questions, see what warranty comes with an oxygen plant, what training a PSA supplier should provide and whether an oxygen tender should require local after-sales service.

More questions

How long was the warranty in tender 402407?

The related services list asks for a written warranty of 24 months from commissioning, for technical failures of the plant's components.

Did the tender ask for a representative in Paraguay?

Addendum No. 11 says an international company that wins the contract needs a technical and legal representative installed in Paraguay to act as the link between the parties.