Oxygen and PSA
Can a PSA plant be commissioned with remote support?
Can a PSA oxygen plant be installed and commissioned by local technicians with remote support from the manufacturer, and what must be on site?
Short answer
In UNDP procurement (REQ-OXY-001, effective 1 January 2025), a PSA plant shall be installed and configured with manufacturer-certified competent personnel, and on-site training during commissioning should come from the manufacturer's certified trainers; WHO's December 2024 specifications add at least 72 hours of continuous operation before commissioning, with remote support listed under the warranty.
UNDP's requirements (sections 6.7 and 7.4) make the supplier responsible for the installation work and for comprehensive testing of the complete plant, under the technical oversight of the UNDP project management unit, which is encouraged to engage certified third-party organisations, where available, for independent verification. The plant should be commissioned after comprehensive testing, calibration and performance verification of flow rates, pressures, oxygen concentration, alarms and backup system functionality. Remote diagnostics appear in UNDP's text as part of the service level agreement, next to on-site troubleshooting and staff training.
What WHO asks to happen on site
WHO's Technical specifications for health facility based medical oxygen systems (31 December 2024), which supersede its 2020 interim PSA specifications, leave the detailed requirements for installation, testing and commissioning to the manufacturer, together with a site readiness checklist. Its requirements before commissioning include: the contractor must position and interconnect all components and connect the system to the power supply; tests should follow the manufacturer's protocols, with results cross-checked with the pre-shipment inspection; the automatic switch-over to the secondary or reserve supply is to be verified; and at least 72 hours of continuous operation of the entire system should be performed, with all analysers and alarms, including power failure, checked. WHO asks for user training on site. Under the warranty, of at least 1 year from commissioning, WHO lists remote support 24 hours a day for manufacturer defects, and suggests a service agreement that details the time to respond remotely and on site.
Remote support in other guidance
- WHO's 2020 interim specification, which said it would expire two years after publication, listed remote support for installation, use and maintenance, described on-site training for installation, use and maintenance as preferable, and asked for conformity of the installation to be verified by a certified third party.
- WHO's Foundations of medical oxygen systems (2023) notes that some technologies, such as PSA plants, allow vendors to do remote monitoring, which, where feasible, enables live reporting and tracking of dysfunctions.
- WHO (2024) asks buyers to decide whether training takes place on site, virtually or in a hybrid form, and warns that teams who install, test and commission are not necessarily suitable for or qualified to conduct training.
Checks the hospital can document
The Global Fund's PSA plant commissioning guidelines (28 August 2024) are written for suppliers, principal recipients, technical staff and biomedical engineers. They confirm equipment details from photographs of nameplates or a plant walkthrough video, run the plant uninterrupted for at least 24 hours (3 days is recommended) at maximum flow, confirm the on-screen purity with a handheld analyser, and end with a formal handover meeting between the supplier or its representative and the hospital. A plant is not considered commissioned until these requirements are documented; the checks can be reconfirmed later by designated trained staff or the contracted supplier, and any deviation must be documented and confirmed with the manufacturer. For the full test list, see how a PSA oxygen plant is commissioned.
ULTRAOX
According to the ULTRAOX SC datasheet, the plants are factory pre-electrified, can be totally interconnected on request, and are parameterised and tested in the factory, ready to start on site. On large ULTRAOX SC and ST plants, installation, initial start-up and training of personnel are supervised by Ultra Controlo factory technicians, and the ULTRAOX 2022 datasheet puts all alarms on an interface for remote signalling.
More questions
Who should install a PSA oxygen plant?
In UNDP procurement, the plant shall be installed and configured according to the manufacturer's instructions, with manufacturer-certified competent personnel, and the supplier is responsible for the installation work.
How long should a PSA plant run before commissioning?
WHO (2024) asks for at least 72 hours of continuous operation before commissioning; the Global Fund (2024) sets a minimum of 24 hours uninterrupted at maximum flow and recommends 3 days.
Sources
- UNDP, REQ-OXY-001 v01, Technical and regulatory requirements for oxygen plants (effective 1 January 2025), sections 6.7, 7.4 and 7.5
- WHO, Technical specifications for health facility based medical oxygen systems (31 December 2024), section 1.1, lines 36 to 42, and Continuous training for operators and service providers
- WHO, Technical specifications for PSA oxygen plants, interim guidance (8 June 2020)
- WHO, Foundations of medical oxygen systems (17 February 2023), section 3.4.3
- Global Fund / Build Health International, Overview: PSA Oxygen Plant Commissioning Guidelines (28 August 2024)
- ULTRAOX SC datasheet, p. 3
- ULTRAOX ST datasheet, p. 3
- ULTRAOX datasheet 2022, p. 16
Ultra Controlo figures come from its technical datasheets. Third-party facts were read at the source on the date shown.