How do you plan medical gases for a new hospital?
What decisions must architects and engineers make about medical gases early in a new hospital project?
Short answer
Early in a new hospital project, the design team should settle each room's gases and terminal units, the design and diversified flows, each gas's supply sources (primary, secondary and tertiary in NHS England's HTM 02-01), where plant rooms, manifold rooms and cylinder stores go, and an expansion allowance.
Start from clinical need, with a multidisciplinary group
HTM 02-01 (2026), the NHS England guidance, introduces an informed design process: the pipeline system is designed from a clear understanding of clinical needs, operational risks, technical requirements and future resilience, rather than relying solely on prescriptive formulas or historic norms. Its principles are clarifying the design requirements and constraints, research and investigation including risk assessment, developing design options, and involving a multidisciplinary group, typically the Medical Gas Safety Group (MGSG), at all stages of the design. The guidance's table of terminal units, area valves and local alarms per room is a basis for discussion that should not be applied in isolation; the assessment covers the patient groups, the procedures in each space and the potential for future changes or emergencies such as another pandemic.
Decisions for the design stage
- Rooms: the project team defines and classifies each room or space at the start of the design, so that its gas flow requirements can be established.
- Flows: the design needs the schedule of terminal units, the design flow and pressure at each terminal unit, the diversified flows for each section, the total flow, historical information and risk-based analyses. Sites that are not open 24/7 base demand on their working hours only.
- Expansion: the allowance for expansion and change of use is risk-assessed, generally with a minimum of 25% in the supply system capacity.
- Supply sources: every medical gas should have primary, secondary and tertiary sources, whose types, capacities and locations are set from the design parameters and a risk assessment at the planning stage.
- Locations: mobile cylinder storage is identified early, with fire compartmentation; manifold rooms are sited by a risk assessment with the MGSG, pharmacy and estates, at ground level with level access for delivery vehicles where practicable; plant rooms should give free all-round access for maintenance and for the replacement of major components, and compressor air intakes should be external where possible.
- Gases: the guidance reports that anaesthetic organisations have recommended that piped nitrous oxide should no longer be considered, and it says a single dual-purpose surgical and medical air plant with variable speed drives should be specified.
Choosing the oxygen source
HTM 02-01 says that for smaller facilities with an annual demand typically below 3000 m³ a cylinder manifold may be the most cost-effective oxygen supply, subject to risk assessment, that liquid oxygen becomes more cost-effective as demand grows, and that future growth should be factored in. It also says PSA should only be considered where geographical or environmental constraints prevent liquid oxygen or cylinder supply, such as remote or offshore locations. WHO's Foundations of medical oxygen systems (2023) asks planners to take account of existing and planned oxygen production, storage and distribution systems. In Portugal, the ACSS ET 03/2006 specification (revised in 2024) requires the oxygen supply to be guaranteed by three sources: primary, secondary and reserve.
Approval, records and testing
Under the guidance, the Authorised Person (MGPS) should review all designs with the support of the Authorising Engineer (MGPS), and the MGSG should review and approve the design before any work starts. A technical file should be created with the design, the components used, their material certificates and the pressure test validation, and updated whenever the system is modified or extended. Validation and verification should start at the design stage, and the contract should define responsibility from the end of quality control testing to handover, including the point at which day-to-day management passes to the Authorised Person.
Ultra Controlo
Ultra Controlo supplies ULTRAOX oxygen plants, ULTRAAR medical air plants, ULTRAVAC vacuum plants and ULTRASEG anaesthetic gas scavenging, as well as MGPS manifolds, valves, alarms, outlets, pendants and headboards.
More questions
How much spare capacity should a new medical gas system have?
HTM 02-01 (2026) says the allowance for expansion and change of use should be risk-assessed, generally with a minimum of 25% built into the supply system capacity.
Who approves a medical gas design under HTM 02-01?
The Authorised Person (MGPS) should review the design with the Authorising Engineer (MGPS), and the Medical Gas Safety Group (MGSG) should approve it before any work starts.
Sources
- NHS England, HTM 02-01 (2026 edition) Part A, paras 1.27 to 1.29, 2.14, 2.23, 2.27, 2.43, 4.4, 4.43, 4.44, 6.11, 6.12, 6.108, 7.6, 15.3, 15.6, 17.81 to 17.139, 19.2 and 19.37
- WHO, Foundations of medical oxygen systems (17 February 2023)
- ACSS, ET 03/2006 v.2024, Gases medicinais
- Ultra Controlo, Medical gas answers (product menu)
- ultracontrolo.com: Medical gas pipeline systems
Ultra Controlo figures come from its technical datasheets. Third-party facts were read at the source on the date shown.