What should a medical gas pipeline tender specify?

What should the technical specification of a medical gas pipeline tender include?

Short answer

A medical gas pipeline tender should specify the gases and terminal units for each room with their design flows, the supply sources, the standards to follow (ISO 7396-1 or its national adoption, plus national guidance), the materials and components, the contractor's qualifications, the testing and commissioning programme, and the documents to hand over.

Request a quote

Standards

WHO's Foundations of medical oxygen systems (2023) names ISO 7396-1, HTM 02-01 and NFPA 99 as the three reference standards widely used for medical gas pipeline design. ISO 7396-1 covers the design, installation, function, performance, testing, commissioning and documentation of pipeline systems, including supply systems, distribution, control, monitoring and alarm systems and non-interchangeability between gases. Its current edition is ISO 7396-1:2016 with Amendment 1 of 2017, adopted in Europe as EN ISO 7396-1:2016 + A1:2019, and a fourth edition is under publication. WHO adds that national authorities indicate the applicable local standard: in Portugal, the ACSS ET 03/2006 specification (last revised in June 2024); in England, HTM 02-01 (2026); in the United States, NFPA 99, whose current edition is 2027.

Design basis

HTM 02-01 (2026), the NHS England guidance, lists the information needed to design the system: the schedule of terminal units, the design flow and pressure at each terminal unit, the diversified flows for each section, the total flow, historical information and risk-based analyses. It asks for primary, secondary and tertiary sources for every medical gas, a risk-assessed allowance for expansion of generally at least 25% of supply capacity, and approval of the design by the Medical Gas Safety Group before work starts.

Materials and components

  • Pipe: seamless copper tube to EN 13348 (6 to 219 mm outside diameter, for up to 2,000 kPa), which HTM 02-01 and the ACSS specification both call for. On minimum pipe diameters, HTM 02-01 is not consistent for the drops to individual terminal units (compare paragraphs 4.5 and 4.110 with paragraph 15.11); ACSS requires brazing solder with at least 40% silver.
  • Terminal units: ISO 9170-1, which covers gas-specific assembly, flow, leakage and pressure drop and prevents interchange between gases, but does not fix probe dimensions.
  • Pressure regulators: ISO 10524-2 for manifold and line pressure regulators.
  • Hoses: ISO 5359. HTM 02-01 asks for hose specifications to be set at the design stage and for hoses to be replaced every five years.
  • Anaesthetic gas scavenging: ISO 7396-2, with terminal units to ISO 9170-2.
  • Bed-head units and pendants: ISO 11197, under which a party that assembles such a unit on site is considered its manufacturer.

Who may do the work

HTM 02-01 says the work should be carried out only by approved specialist contractors registered to BS EN ISO 9001 and/or BS EN ISO 13485 with a scope covering it (for example design, installation, commissioning, validation, verification and maintenance), using Competent Persons (MGPS) who are trained and on a register. Engineering validation and verification should be done only by contractors registered to BS EN ISO 9001, quality control testing by a Quality Controller (MGPS) on the register, and the Authorising Engineer, Authorised Person and Quality Controller should be independent of each other and of the installer.

Testing, handover and records

The HTM 02-01 test programme has four phases, ending with identity, quality and purity tests of the gases by the Quality Controller before handover to clinical staff, and all components should be tested rather than a sample. The contract should define responsibility from the end of quality control testing to final handover, including the point at which day-to-day management passes to the Authorised Person. Handover includes a completion certificate (form B33) signed by the key personnel, as-fitted drawings verified against the installed pipeline, and a technical file with the design, the components, their material certificates and the pressure test validation, updated with every later modification. In Portugal, ACSS requires the tests set out in ISO 7396-1 and ISO 7396-2.

Ultra Controlo

Ultra Controlo supplies MGPS components (manifolds, valves, alarms, outlets, pendants and headboards).

More questions

Which standard governs hospital medical gas pipelines?

ISO 7396-1 is the international standard, adopted in Europe as EN ISO 7396-1:2016 + A1:2019; WHO also names HTM 02-01 and NFPA 99 as widely used references.

Who tests a new medical gas pipeline under HTM 02-01?

Engineering tests are done by the Competent Person (MGPS), and the final identity, quality and purity tests by a Quality Controller (MGPS) independent of the installer.