How were World Bank oxygen units procured in Burkina Faso?

How did Burkina Faso's World Bank financed COVID-19 project procure oxygen production units?

Short answer

World Bank procurement notices show that under Burkina Faso's COVID-19 Preparedness and Response Project (P173858) oxygen production units for the regional hospitals of Dori, Kaya and Gaoua were procured by direct selection, in a notice of 17 August 2023 that gives a 240-day contract duration and covers acquisition, installation and commissioning.

Two notices read on 19 November 2026 under project P173858 concern oxygen. They are summarised without the firms or prices.

Scope as publishedMethodNotice dateDuration
Supply of medical fluids for intensive care at the Tengandogo university hospitalDirect selection (gré à gré)8 November 20207 days
Acquisition, installation and commissioning of oxygen production units to strengthen autonomous production in the regional hospitals of Dori, Kaya and GaouaDirect selection (gré à gré)17 August 2023240 days

What the table shows

The 2020 notice is a small-assignment award for the supply of medical fluids, signed on 30 October 2020. It is a supply for intensive care, not an oxygen plant. The 2023 notice is the one for production units: its title says the units are meant to strengthen the hospitals' autonomous production, and the notice lists the contract duration as 240 days. Its date of notification of award is shown as null on the notice.

What this page does not cover

The notices do not say what technology the units use, their capacity, or whether they are working today. The notices of other funders in Burkina Faso, and national tenders, are not covered. For where regional buyers publish, see where oxygen plant tenders are published in francophone Africa, and for a comparison with a neighbour, see how World Bank oxygen plant tenders are run in Côte d'Ivoire.

More questions

Which hospitals does the 2023 notice name?

The regional hospitals of Dori, Kaya and Gaoua, according to the World Bank notice of 17 August 2023 for project P173858.

Sources

Ultra Controlo figures come from its technical datasheets. Third-party facts were read at the source on the date shown.

Reviewed: · Ultra Controlo engineering · Markdown version

Related