Oxygen and PSA
What maintenance does a PSA oxygen plant need?
What preventive maintenance does a PSA oxygen plant need, and how often?
Short answer
A PSA oxygen plant needs daily operator checks plus preventive maintenance on the manufacturer's schedule: filter changes, condensate drains, compressor service, calibration of oxygen sensors and pressure gauges, and recharging of the sieve beds when capacity or purity falls. Intervals depend on the equipment, so the supplier should hand over a written maintenance plan.
A typical schedule
Each manufacturer sets its own intervals and schedule, as Global Fund guidance points out. The table combines a USAID operating procedure for PSA plants (2022), written for hospitals in India, with Global Fund and PATH guidance, as an example of what a plan covers.
| When | Task | Source |
|---|---|---|
| Daily | Inspect the pre-filter, oxygen purity, compressor pressure and oil level, tank pressures and dryer dew point; check the drains | USAID RISE SOP; Global Fund daily checklist |
| Monthly | Check pipes and hoses for leaks and solenoid valves for corrosion; inspect the carbon, fine and bacterial filters; test the automatic drain valve | USAID RISE SOP |
| Every three or six months | Calibrate pressure regulators and gauges, as the manufacturer recommends | USAID RISE SOP |
| Every six months (preferably) | Have oxygen samples tested by an accredited laboratory to validate the plant and its oxygen analyser | USAID RISE SOP |
| Yearly | Check the drying and regeneration cycles, silencers and valve seals; replace filter elements; calibrate the oxygen sensor; check compressor and dryer servicing | USAID RISE SOP |
| By running hours | Service at the manufacturer's intervals; check the manual approaching every 500 and 1,000 hours, with 2,000, 4,000 and 8,000 hours common milestones | Global Fund expected values (2025) |
| When performance falls | Recharge the sieve beds if generating capacity or purity drops; rebuild a valve assembly or compressor after a failure | PATH and CHAI (2021) |
Who does it, and what to keep on site
PATH notes that preventive maintenance needing trained engineers, such as cleaning or replacing filters, draining water or oil traps, replacing lubricants and calibrating pressure and oxygen sensors, can be contracted to the manufacturer. The USAID procedure says preventive maintenance should only be done by experienced, properly trained personnel. Global Fund sustainability guidance strongly advises a long-term warranty and maintenance contract of 5 years, recommends a spare parts inventory of at least two years, and asks for records of daily checklists, preventive maintenance and repairs. At commissioning, the supplier should hand over a preventive maintenance schedule with the service interval and parts kit for each item of equipment.
ULTRAOX plants
The ULTRAOX SC datasheet states one service at 10,000 hours for the plant with oil-less ULTRACECO compressors. The ULTRAOX datasheet states that in good conditions the zeolite can last up to 10 years or more without replacement, and the plant is designed for a minimum life cycle of 150,000 hours. The ULTRAOX touch screen shows maintenance information with the next intervention due. Preventive maintenance and monitoring are offered through the UltraCare programme.
More questions
How often does PSA zeolite need replacing?
There is no fixed interval: PATH says sieve beds must be recharged if capacity or purity falls, and the ULTRAOX datasheet states the zeolite can last up to 10 years or more in good conditions.
How long should a PSA maintenance contract be?
Global Fund sustainability guidance strongly advises a long-term warranty and maintenance contract of 5 years.
Sources
- USAID RISE, SOP: PSA Plant Operations and Preventive Maintenance (March 2022)
- Global Fund / Build Health International, PSA plant Daily Maintenance Checklist (2025)
- Global Fund / Build Health International, Daily checklist expected values (5 June 2025, French)
- PATH and CHAI, Oxygen Generation and Storage: Pressure/Vacuum Swing Adsorption Plant (July 2021)
- Global Fund / Build Health International, Overview: Sustainability Guidance for PSA Oxygen Plants (22 August 2024)
- Global Fund / Build Health International, Overview: PSA Oxygen Plant Commissioning Guidelines (28 August 2024)
- ULTRAOX SC datasheet, p. 2; ULTRAOX datasheet 2022, p. 4 and p. 16
- ultracontrolo.com: UltraCare
Ultra Controlo figures come from its technical datasheets. Third-party facts were read at the source on the date shown.