Which Incoterms are used when buying an oxygen plant abroad?
Which Incoterms are used when an oxygen plant is bought internationally, and how do they split shipping, installation and risk?
Short answer
UNOPS and CHAI oxygen plant tenders published in 2022 specify an Incoterms 2020 rule for delivering the plant: UNOPS used CPT, with installation, testing, commissioning, training and after-sales services also in the scope, and CHAI used DAP, with customs clearance, if needed, done by CHAI.
Examples from published tenders
| Tender | Incoterms 2020 rule | What else the notice states |
|---|---|---|
| UNOPS, ITB/2022/43573, two PSA oxygen plants (published 14 September 2022) | CPT | Supply and delivery including installation, testing, commissioning, training and after-sales services |
| CHAI, RFP/CHAI/OSC/0122, containerised PSA plant with cylinder filling station (posted 9 May 2022) | DAP | Customs clearance and duties, if needed, done by CHAI; transport by sea |
WHO's Foundations of medical oxygen systems (2023) lists shipping methods, insurance and trade terms such as Incoterms among the factors that make the acquisition cost of a PSA system vary.
Where each rule puts delivery, cost and risk
The International Chamber of Commerce (ICC) publishes the Incoterms rules: eleven three-letter trade terms for contracts for the sale and purchase of goods. HM Revenue and Customs groups seven of the rules as rules for any mode of transport and four as rules for sea and inland waterway transport, and the US International Trade Administration notes that each rule sets when the risk of loss or damage passes from seller to buyer by reference to its delivery provision. The rules for any mode of transport, as summarised by HM Revenue and Customs (June 2025):
| Rule | Summary |
|---|---|
| EXW, Ex Works | The seller places the goods at the buyer's disposal at its premises or another named place, without loading them or clearing them for export |
| FCA, Free Carrier | The seller delivers to the carrier or person nominated by the buyer at a named place; the risk passes to the buyer at that point |
| CPT, Carriage Paid To | The seller delivers to a carrier it nominates and contracts and pays for carriage to the named place of destination |
| CIP, Carriage and Insurance Paid To | As CPT, and the seller also contracts insurance against the buyer's risk during carriage; ICC says the 2020 rule requires cover compliant with the Institute Cargo Clauses (A) or similar |
| DAP, Delivered at Place | The seller delivers on the arriving means of transport, ready for unloading at the named destination, and bears all risks to that place |
| DPU, Delivered at Place Unloaded | As DAP, but the seller also unloads the goods at the named destination and bears that risk |
| DDP, Delivered Duty Paid | The seller delivers cleared for import, bears all costs and risks to the destination, and clears export and import and pays the duties |
What Incoterms leave to the contract
According to the US International Trade Administration, Incoterms do not address all the conditions of a sale: they do not set the price or the method and timing of payment, say when title passes, specify the documents needed for customs clearance in the buyer's country, or deal with liability for non-conforming goods, delayed delivery or disputes, and the parties need to state which version they use. In the UNOPS tender above, installation, testing, commissioning, training and after-sales services were part of the scope alongside the CPT delivery term. The wider contract scope is covered in what is included in a turnkey PSA contract and how a PSA plant is delivered and installed.
More questions
What is the difference between DAP and DPU?
According to the ICC, under DAP the seller does not unload the goods at the destination, while under DPU the seller does unload them.
Do Incoterms cover delay penalties?
No. The US International Trade Administration notes that Incoterms do not address liability for delayed delivery.
Sources
- UNOPS, ITB/2022/43573, Supply and installation of 2 PSA oxygen generating plants, notice on UNGM (published 14 September 2022)
- Clinton Health Access Initiative, RFP/CHAI/OSC/0122, containerised PSA oxygen plant with cylinder filling station (posted 9 May 2022)
- WHO, Foundations of medical oxygen systems (17 February 2023), section 2.4
- International Chamber of Commerce, Incoterms 2020 (web page, read 23 October 2026)
- US International Trade Administration, Know your Incoterms (web page, read 23 October 2026)
- HM Revenue and Customs, Customs valuation guidance: Incoterms (published 25 June 2025)
Ultra Controlo figures come from its technical datasheets. Third-party facts were read at the source on the date shown.
Related
- AnswersWhat is included in a turnkey oxygen plant contract?
- AnswersHow is a PSA oxygen plant delivered and installed?
- AnswersWhat should a hospital check when comparing PSA bids?
- AnswersCan a PSA tender set a maximum kWh per cubic metre?
- AnswersDoes Ultra Controlo train hospital staff?
- AnswersHow can a ministry train enough technicians for its oxygen plants?