How did a 2025 UNOPS Laos tender set the oxygen plant room and backup?

What did UNOPS's clarifications to its 2025 Laos medical gas tender say about the plant room, oxygen redundancy, cylinder backup and power?

Short answer

According to the clarifications on UNOPS invitation to bid ITB/2025/55458 (January to February 2025), the Laos plant room was set at 72 sqm with one 2 m wide door, the oxygen supply needed a main line and a back-up line, and the UPS needed at least 30 minutes of autonomy.

Request a quoteBuying a PSA oxygen plant in Laos

This answer reads the clarifications and amendments on one public UNGM notice. The answers quoted are UNOPS's replies to questions from prospective bidders, not general design rules. The tender is closed, and the values below are those of this one hospital project.

What UNOPS answered

TopicUNOPS answer or amendment
Plant room floor areaRevised to 45 sqm on 20 January 2025 (amendment 3), then to 72 sqm in answers of 29 January 2025, which said two walls would be demolished; UNOPS said the space could not be increased to 170 sqm
Plant room doorOne door, 2 m wide and 2.6 m high
Oxygen redundancyTwo independent lines able to guarantee continuous supply, one main line and one back-up line; the second generator was for back-up and filling
Compressor typeAsked to offer standard oiled compressors instead of oil-free ones, UNOPS replied: "Please adhere to the requirement."
Cylinder back-upA 2x10 automatic change over was accepted as sufficient
Medical airThe requirement was for 3 compressors
VacuumAt least two pumps
Single failureThe design had to keep supplying oxygen and medical air under a single failure of any component
UPSUPS devices protecting the controllers of the oxygen and medical air generation systems against micro power outages had to provide at least 30 minutes of autonomy (amendment 8, 3 February 2025)
Oxygen booster outputLowered from at least 80 m³/hr to at least 30 m³/hr (amendment 7, 3 February 2025)

What the design memory had to cover

UNOPS told bidders to explain their design criteria in a document called the design memory, including the equipment, capacity, technology, number of compression units and type of monitoring, and a review of the design according to HTM 02-01:2006, with schematic diagrams. The tender cites that 2006 edition; HTM 02-01 is NHS England guidance, and for its current edition see what changed in the 2026 edition of HTM 02-01.

What it means for a supplier

The clarifications show how much of a plant's design was settled by questions during the bidding period: room size changed twice, and the booster output and the UPS were amended after bidders asked. Anyone reading a similar tender should check the amendments and clarifications as well as the main documents. For backup power in general, see whether a PSA plant needs a backup generator or UPS.

More questions

Was the plant room finished when the tender ran?

No. UNOPS said the space was not ready and that works were to be completed within the next two months.

Does this set a rule for other countries?

No. These are answers to bidders on one UNOPS tender for Laos.