How should a hospital prioritise which equipment is maintained first when it has too few technicians?

Short answer

WHO's Medical equipment maintenance programme overview (2011) says a hospital should carefully identify the equipment that is most important to inspect and maintain and schedule that work first, in a tiered process, instead of planning to service everything and leaving critical equipment unserviced.

WHO's 2011 overview, part of its Medical device technical series, notes that exact matches between the workload for the equipment in a hospital and the staff available to do the work are rare. It says that creating a tiered process, where the most important equipment is dealt with first, is a better use of limited resources, and that when additional staff is added and their training completed, the next lower tier of equipment can be added to the schedule.

Four ways WHO lists to rank equipment

In this section WHO uses IPM for inspection and preventive maintenance and CM for corrective maintenance. It lists the following methods of prioritizing:

  • Risk-based: the highest priority goes to equipment with the highest likelihood of causing patient injury if it fails.
  • Mission-based: the question is which devices are most important in providing the majority of the hospital's patient care, and that equipment becomes the priority.
  • Maintenance-based: the method looks at which devices have a significant potential to harm a patient if they do not function properly and a significant potential to function improperly if they are not provided with an adequate level of IPM. Devices excluded are those for which there is no evidence that they benefit from scheduled IPM.
  • Resource-based: any of the three methods above is combined with knowledge about the staffing and resource levels of the particular facility or region, to define maintenance priorities.

Other reasons WHO mentions

WHO adds that priority may also be given to IPM and CM of equipment that generates revenue for the health-care organization, and when the non-availability of equipment incurs higher costs, for example the costs of temporary rental of replacement equipment. For unscheduled repairs, WHO says it is important to have a prioritization scheme in place so that CM resources are directed toward the most critical needs. WHO's guide to computerized maintenance management systems (2011) adds that priority levels for preventive or corrective work can be assigned with reference to the equipment risk, the strategic value to the health facility, and the availability of back-up equipment.

The guide is written for medical equipment in general. For the planned work on a specific plant, see what maintenance a PSA oxygen plant needs, and for the choice between a hospital team and a contractor see in-house vs outsourced maintenance.

More questions

What is a tiered maintenance process?

In WHO's 2011 overview it is a process where the most important equipment is dealt with first, with the next lower tier added when additional staff is added and their training completed.

Does WHO say all equipment must be maintained on a schedule?

No. Under the maintenance-based method in WHO's 2011 overview, devices excluded are those for which there is no evidence that they benefit from scheduled IPM.