How were World Bank oxygen plants procured in Niger?

How did Niger's World Bank financed COVID-19 project procure oxygen plants and related equipment?

Short answer

World Bank procurement notices show that under Niger's COVID-19 Emergency Response Project (P173846) the oxygen production plants for the regional health directorates of Tahoua, Zinder and Maradi were procured by direct selection, with installation and user training in the scope, while a booster and oxygen concentrators for SAMU ambulances were bought by Request for Quotations.

The notices read on 19 November 2026 list project P173846 and show different methods for different items. The table summarises the notices for oxygen plants, the booster and the concentrators, without the winning firms or prices.

Item (scope as published)MethodNotice date
Oxygen concentrators for health facilitiesDirect selection (gré à gré)5 October 2020
Oxygen plant for the Tahoua regional health directorateDirect selection (gré à gré)31 March 2021
Three oxygen plants for the Tahoua, Zinder and Maradi directorates, including user trainingDirect selection13 September 2023
10 oxygen concentrators with autonomy for SAMU ambulancesRequest for Quotations4 April 2024
5 oxygen concentrators with autonomy for SAMU ambulancesRequest for Quotations24 July 2024
Booster for the oxygen production unit of the Niamey National Hospital, with installationRequest for Quotations19 December 2024

What the table shows

The 2021 notice records a contract signed on 12 March 2021 with a 105-day duration. The 2023 notice records a notification of award on 12 April 2023 and a 3-month duration. The booster notice records a notification of award on 29 November 2024 and a 1-month duration. The notices are those of the Bank's project site, and Niger's notices of other funders are not covered here. A notice of 23 March 2023 for the supply of nasal cannulas for concentrators, by Request for Quotations, is not listed.

The Bank's notices say how a purchase was made, not whether the equipment is working. For what happens after handover, see how a donor funded oxygen plant is handed over to the ministry and what happens when a hospital PSA plant has no maintenance contract.

More questions

Which method did the 2023 notice for three plants use?

Direct selection, according to the World Bank notice of 13 September 2023 for project P173846.

Why does a booster appear in the list?

A notice of 19 December 2024 covers the supply and installation of a booster for the oxygen production unit of the Niamey National Hospital, by Request for Quotations.